Timeline

Anchored on Oct 1, 2026. Assumes an accepted offer in September 2026 and closing on October 1. Move the anchor when there is a real contract date. Columns follow the site convention: Favorable is the shortest path.

Done (Favorable)
May 2028
May 15, 2028 · 20 months · first ski season Dec 2028 · Construction slips Apr 1, 2027 → Apr 15, 2027
Done (Mid)
Nov 2028
Nov 1, 2028 · 25 months · first ski season Dec 2028
Done (Unfavorable)
Dec 2029
Dec 15, 2029 · 39 months · first ski season Dec 2029 · Construction slips Feb 1, 2028 → Apr 15, 2028

Phases

PhaseMonths (Favorable / Mid / Unfavorable)Ends (mid)Source
Offer, due diligence, closingCovenants, plat, tap status, HOA/metro-district letters.1 / 2 / 3Dec 2026Model estimate — lot contract to closing incl. covenant and survey review; replace with cited source unverified · low
Architect completes plans to permit setShorter if the Hill plans are already at DD.3 / 5 / 8May 2027Model estimate — DD→CD completion with lock-off revision; replace with cited source unverified · low
Prospect design review and Mt. CB permit2 / 3 / 5Aug 2027Model estimate — DRB + town plan check; replace with cited source unverified · low
Builder bids and contract1 / 2 / 3Jul 2027Model estimate — GC bidding in a busy valley; replace with cited source unverified · low
ConstructionSame assumption as the construction loan term. Excavation cannot start Oct 15–Apr 15 (no tapping), so a start inside that window slips to April 15.12 / 14 / 18Oct 2028Model estimate — build duration in Mt. CB (short season); replace with cited source unverified · low
Furnishing, CO, STR license1 / 1 / 2Nov 2028Model estimate — punch list, certificate of occupancy, licensing; replace with cited source unverified · low

Mid-case schedule

Bars share one axis scaled to the unfavorable total of 39 months.

Excavation-blackout slips (no construction start Oct 15–Apr 15): Favorable: Construction slips Apr 1, 2027 → Apr 15, 2027; Unfavorable: Construction slips Feb 1, 2028 → Apr 15, 2028.