Build cost
Parametric estimate: $/sf by space type plus lot-specific line items. All inputs are unverified model estimates until builders and the architect weigh in.
Base plan (mid)
$6.73M
$4.91M – $9.02M · $1,447/sf
Lock-off variant (mid)
$6.86M
$4.99M – $9.24M · $1,475/sf
Lock-off premium
$130K
$76K – $215K
Base plan
Hill Residence plans as drawn: single-family, lower level open to main stair.
| Item | Low | Mid | High |
|---|---|---|---|
| Conditioned space (4,650 sf)Rough takeoff from dimension strings on the photographed Hill Residence sheets (±10%) | $3,487,500 | $4,417,500 | $5,580,000 |
| Garage | $225,000 | $292,500 | $360,000 |
| Decks / patios | $50,000 | $75,000 | $100,000 |
| Crawl space | $48,000 | $72,000 | $96,000 |
| Item | Low | Mid | High |
|---|---|---|---|
| Architect: complete plans to permit setdesign | $60,000 | $90,000 | $130,000 |
| Structural, civil, geotechdesign | $25,000 | $40,000 | $60,000 |
| Prospect design review (PUD guide / Design Guidelines 2013)fees | $3,000 | $5,000 | $8,000 |
| Mt. CB building permit, plan review & materials use taxfees | $60,000 | $90,000 | $120,000 |
| Water & sewer tap feesfees | $30,000 | $45,000 | $60,000 |
| Utility extensions (power, gas, comms)site | $20,000 | $35,000 | $60,000 |
| Excavation & foundation premium (slope)site | $75,000 | $125,000 | $200,000 |
| Driveway, grading, landscapingsite | $40,000 | $70,000 | $110,000 |
| Item | Low | Mid | High |
|---|---|---|---|
| Hard cost subtotal | $3,810,500 | $4,857,000 | $6,136,000 |
| Soft costs, fees, site | $313,000 | $500,000 | $748,000 |
| Builder feeApplied to hard cost only | $457,260 | $728,550 | $1,104,480 |
| ContingencyApplied to hard cost + line items | $329,880 | $642,840 | $1,032,600 |
| Build total | $4,910,640 | $6,728,390 | $9,021,080 |
Lock-off variant
Lower level converted to a lockable rental unit with kitchenette and private entry.
| Item | Low | Mid | High |
|---|---|---|---|
| Conditioned space (4,650 sf)Rough takeoff from dimension strings on the photographed Hill Residence sheets (±10%) | $3,487,500 | $4,417,500 | $5,580,000 |
| Garage | $225,000 | $292,500 | $360,000 |
| Decks / patios | $50,000 | $75,000 | $100,000 |
| Crawl space | $48,000 | $72,000 | $96,000 |
| Item | Low | Mid | High |
|---|---|---|---|
| Architect: complete plans to permit setdesign | $60,000 | $90,000 | $130,000 |
| Structural, civil, geotechdesign | $25,000 | $40,000 | $60,000 |
| Prospect design review (PUD guide / Design Guidelines 2013)fees | $3,000 | $5,000 | $8,000 |
| Mt. CB building permit, plan review & materials use taxfees | $60,000 | $90,000 | $120,000 |
| Water & sewer tap feesfees | $30,000 | $45,000 | $60,000 |
| Utility extensions (power, gas, comms)site | $20,000 | $35,000 | $60,000 |
| Excavation & foundation premium (slope)site | $75,000 | $125,000 | $200,000 |
| Driveway, grading, landscapingsite | $40,000 | $70,000 | $110,000 |
| Architect revision for lock-offlockoff | $15,000 | $25,000 | $40,000 |
| Kitchenettelockoff | $25,000 | $40,000 | $60,000 |
| Fire separation, lockable vestibule at stairlockoff | $10,000 | $18,000 | $30,000 |
| Separate exterior entry & pathlockoff | $15,000 | $25,000 | $45,000 |
| Separate utility metering / sub-panellockoff | $5,000 | $8,000 | $12,000 |
| Item | Low | Mid | High |
|---|---|---|---|
| Hard cost subtotal | $3,810,500 | $4,857,000 | $6,136,000 |
| Soft costs, fees, site | $383,000 | $616,000 | $935,000 |
| Builder feeApplied to hard cost only | $457,260 | $728,550 | $1,104,480 |
| ContingencyApplied to hard cost + line items | $335,480 | $656,760 | $1,060,650 |
| Build total | $4,986,240 | $6,858,310 | $9,236,130 |
Assumptions
| Item | Low | Mid | High |
|---|---|---|---|
| Conditioned space $/sfBlog cites $800–1,500/sf for "vertical construction incl. site work"; site work is a separate line here, so the band sits below that range. Ask 2–3 local builders. | $750 | $950 | $1,200 |
| Garage $/sf | $250 | $325 | $400 |
| Decks / patios $/sf | $100 | $150 | $200 |
| Crawl space $/sf | $40 | $60 | $80 |
| Assumption | Source |
|---|---|
| Conditioned space rate | Chris Kopf Crested Butte Real Estate, "Calculating cost to build your Crested Butte home" (search snippet; page blocked fetch) unverified · low |
| Garage rate | Model estimate — heated garage $/sf; replace with cited source unverified · low |
| Decks / patios rate | Model estimate — covered/uncovered deck $/sf; replace with cited source unverified · low |
| Crawl space rate | Model estimate — unfinished crawl space $/sf; replace with cited source unverified · low |
| Architect: complete plans to permit set | Model estimate — DD→CD completion for ~4,650 sf custom; replace with cited source unverified · lowDepends on plan phase — ask architect. |
| Structural, civil, geotech | Model estimate — engineering for sloped mountain lot; replace with cited source unverified · low |
| Prospect design review (PUD guide / Design Guidelines 2013) | Crested Butte Real Estate (cbliving.com), "Prospect documents" — PUD guide, CC&Rs, Design Guidelines 2013, Reserve Metro District No. 2 unverified · lowProspect is governed by a recorded PUD guide, CC&Rs and Reserve Metro District No. 2; no fee schedule found. Get the recorded covenants from the title company. |
| Mt. CB building permit, plan review & materials use tax | Town of Mt. Crested Butte, "Total Valuation & Building Materials Policy" and "Use Tax Information" (search snippets; PDFs blocked fetch) unverified · lowTown charges 3% use tax on materials (assumed 50% of valuation) ≈ 1.5% of valuation, plus permit fee and plan check at 65% of permit fee. Fee table not retrieved; confirm with the building department. |
| Water & sewer tap fees | Mt. Crested Butte Water & Sanitation District, "Tap Fees" (structure only; 2026 fee PDF unreadable) unverified · lowFees scale with floor area plus fixtures; $150 application, stamped plans, 14-day turnaround; no tapping Oct 15–Apr 15. May already be paid — ask agent. |
| Utility extensions (power, gas, comms) | Model estimate — utility extension on Prospect lot; replace with cited source unverified · low |
| Excavation & foundation premium (slope) | Model estimate — sloped-lot excavation/retaining premium; replace with cited source unverified · low |
| Driveway, grading, landscaping | Model estimate — mountain driveway + revegetation; replace with cited source unverified · low |
| Architect revision for lock-off | Model estimate — plan revision + resubmittal; replace with cited source unverified · low |
| Kitchenette | Model estimate — compact kitchen incl. plumbing/electrical; replace with cited source unverified · low |
| Fire separation, lockable vestibule at stair | Model estimate — rated assembly + door; replace with cited source unverified · low |
| Separate exterior entry & path | Model estimate — entry door, steps, lighting, snow path; replace with cited source unverified · low |
| Separate utility metering / sub-panel | Model estimate — sub-metering; replace with cited source unverified · low |
| Builder fee | Model estimate — GC fee on hard cost; replace with cited source unverified · low |
| Contingency | Model estimate — owner contingency on hard + soft; replace with cited source unverified · low |