CB House605 Prospect Drive

Build cost

Parametric estimate: $/sf by space type plus lot-specific line items. All inputs are unverified model estimates until builders and the architect weigh in.

Base plan (mid)
$6.08M
$4.31M – $8.32M · $1,307/sf
Lock-off variant (mid)
$6.21M
$4.39M – $8.54M · $1,335/sf
Lock-off premium
$130K
$76K – $215K

Base plan

Hill Residence plans as drawn: single-family, lower level open to main stair.

Hard costs
ItemLowMidHigh
Conditioned space (4,650 sf)Areas measured roughly from dimension strings on photographed sheets (±10%). Replace with the architect's area table.$3,022,500$3,952,500$5,115,000
Garage$225,000$292,500$360,000
Decks / patios$50,000$75,000$100,000
Crawl space$48,000$72,000$96,000
Line items
ItemLowMidHigh
Architect: complete plans to permit setdesign$60,000$90,000$130,000
Structural, civil, geotechdesign$25,000$40,000$60,000
Prospect HOA design reviewfees$3,000$5,000$8,000
Mt. CB building permit & plan reviewfees$25,000$35,000$50,000
Water & sewer tap feesfees$30,000$45,000$60,000
Utility extensions (power, gas, comms)site$20,000$35,000$60,000
Excavation & foundation premium (slope)site$75,000$125,000$200,000
Driveway, grading, landscapingsite$40,000$70,000$110,000
Roll-up
ItemLowMidHigh
Hard cost subtotal$3,345,500$4,392,000$5,671,000
Soft costs, fees, site$278,000$445,000$678,000
Builder fee$401,460$658,800$1,020,780
Contingency$289,880$580,440$952,350
Build total$4,314,840$6,076,240$8,322,130

Lock-off variant

Lower level converted to a lockable rental unit with kitchenette and private entry.

Hard costs
ItemLowMidHigh
Conditioned space (4,650 sf)Areas measured roughly from dimension strings on photographed sheets (±10%). Replace with the architect's area table.$3,022,500$3,952,500$5,115,000
Garage$225,000$292,500$360,000
Decks / patios$50,000$75,000$100,000
Crawl space$48,000$72,000$96,000
Line items
ItemLowMidHigh
Architect: complete plans to permit setdesign$60,000$90,000$130,000
Structural, civil, geotechdesign$25,000$40,000$60,000
Prospect HOA design reviewfees$3,000$5,000$8,000
Mt. CB building permit & plan reviewfees$25,000$35,000$50,000
Water & sewer tap feesfees$30,000$45,000$60,000
Utility extensions (power, gas, comms)site$20,000$35,000$60,000
Excavation & foundation premium (slope)site$75,000$125,000$200,000
Driveway, grading, landscapingsite$40,000$70,000$110,000
Architect revision for lock-offlockoff$15,000$25,000$40,000
Kitchenettelockoff$25,000$40,000$60,000
Fire separation, lockable vestibule at stairlockoff$10,000$18,000$30,000
Separate exterior entry & pathlockoff$15,000$25,000$45,000
Separate utility metering / sub-panellockoff$5,000$8,000$12,000
Roll-up
ItemLowMidHigh
Hard cost subtotal$3,345,500$4,392,000$5,671,000
Soft costs, fees, site$348,000$561,000$865,000
Builder fee$401,460$658,800$1,020,780
Contingency$295,480$594,360$980,400
Build total$4,390,440$6,206,160$8,537,180

Assumptions

Unit rates ($/sf)
ItemLowMidHigh
Conditioned space $/sfAsk 2–3 local builders for current $/sf.$650$850$1,100
Garage $/sf$250$325$400
Decks / patios $/sf$100$150$200
Crawl space $/sf$40$60$80
Sources and confidence
AssumptionSource
Conditioned space rateModel estimate — custom mountain home hard cost per conditioned sf; replace with cited source unverified · low
Garage rateModel estimate — heated garage $/sf; replace with cited source unverified · low
Decks / patios rateModel estimate — covered/uncovered deck $/sf; replace with cited source unverified · low
Crawl space rateModel estimate — unfinished crawl space $/sf; replace with cited source unverified · low
Architect: complete plans to permit setModel estimate — DD→CD completion for ~4,650 sf custom; replace with cited source unverified · lowDepends on plan phase — ask architect.
Structural, civil, geotechModel estimate — engineering for sloped mountain lot; replace with cited source unverified · low
Prospect HOA design reviewModel estimate — Prospect DRB fees; replace with cited source unverified · low
Mt. CB building permit & plan reviewModel estimate — Town of Mt. Crested Butte permit schedule; replace with cited source unverified · low
Water & sewer tap feesModel estimate — Mt. CB Water & Sanitation District tap fees; replace with cited source unverified · lowMay already be paid — ask agent.
Utility extensions (power, gas, comms)Model estimate — utility extension on Prospect lot; replace with cited source unverified · low
Excavation & foundation premium (slope)Model estimate — sloped-lot excavation/retaining premium; replace with cited source unverified · low
Driveway, grading, landscapingModel estimate — mountain driveway + revegetation; replace with cited source unverified · low
Architect revision for lock-offModel estimate — plan revision + resubmittal; replace with cited source unverified · low
KitchenetteModel estimate — compact kitchen incl. plumbing/electrical; replace with cited source unverified · low
Fire separation, lockable vestibule at stairModel estimate — rated assembly + door; replace with cited source unverified · low
Separate exterior entry & pathModel estimate — entry door, steps, lighting, snow path; replace with cited source unverified · low
Separate utility metering / sub-panelModel estimate — sub-metering; replace with cited source unverified · low
Builder feeModel estimate — GC fee on hard cost; replace with cited source unverified · low
ContingencyModel estimate — owner contingency on hard + soft; replace with cited source unverified · low