CB House605 Prospect Drive

Financing & carry

Construction-to-permanent loan: lot drawn at closing, build drawn evenly over 14 months (mid), interest-only during construction, then a 30-year mortgage.

Base plan

Project cost stack
ItemLowMidHigh
Lot$650,000$650,000$650,000
Closing costs$6,500$9,750$13,000
Build total$4,314,840$6,076,240$8,322,130
Construction interest$152,802$280,766$521,580
All-in cost$5,124,142$7,016,756$9,506,710
Loan and equity
ItemLowMidHigh
Loan amountLTV 75% (mid)$3,479,938$5,051,993$6,738,848
Equity required (all families)$1,644,204$1,964,764$2,767,863
Permanent mortgage payment / mo$20,864$32,767$47,119
Annual carrying costs
ItemLowMidHigh
Property tax$19,885$33,680$53,911
HOA dues$2,000$3,000$4,500
Insurance$6,000$8,000$12,000
Utilities$5,000$7,000$10,000
Snow removal$3,000$4,000$6,000
Maintenance reserve$8,000$12,000$18,000
Annual carry$43,885$67,680$104,411
Monthly
ItemLowMidHigh
Monthly all-in (mortgage + carry)$24,521$38,407$55,820
Per family
FamilyEquity (low / mid / high)Monthly all-in (low / mid / high)
Redden family (50%)$822K / $982K / $1.38M$12,261 / $19,204 / $27,910
Partner family (50%)$822K / $982K / $1.38M$12,261 / $19,204 / $27,910

Lock-off variant

Project cost stack
ItemLowMidHigh
Lot$650,000$650,000$650,000
Closing costs$6,500$9,750$13,000
Build total$4,390,440$6,206,160$8,537,180
Construction interest$154,808$285,638$533,072
All-in cost$5,201,748$7,151,548$9,733,252
Loan and equity
ItemLowMidHigh
Loan amountLTV 75% (mid)$3,532,858$5,149,433$6,900,135
Equity required (all families)$1,668,890$2,002,116$2,833,117
Permanent mortgage payment / mo$21,181$33,399$48,247
Annual carrying costs
ItemLowMidHigh
Property tax$20,188$34,330$55,201
HOA dues$2,000$3,000$4,500
Insurance$6,000$8,000$12,000
Utilities$5,000$7,000$10,000
Snow removal$3,000$4,000$6,000
Maintenance reserve$8,000$12,000$18,000
Annual carry$44,188$68,330$105,701
Monthly
ItemLowMidHigh
Monthly all-in (mortgage + carry)$24,864$39,093$57,055
Per family
FamilyEquity (low / mid / high)Monthly all-in (low / mid / high)
Redden family (50%)$834K / $1.00M / $1.42M$12,432 / $19,547 / $28,528
Partner family (50%)$834K / $1.00M / $1.42M$12,432 / $19,547 / $28,528

Terms assumed

Rates and ratios
ItemLowMidHigh
Construction rate7.0%8.0%9.0%
Permanent rate (30 yr)6.0%6.8%7.5%
LTVA ratio, not a cost: lower LTV means more family equity. Columns are the low-/mid-/high-cost scenarios; the low-cost scenario pairs cheaper construction with a tighter 70% lender.70.0%75.0%75.0%
Closing costs (% of lot)1.0%1.5%2.0%
Financing assumptions and sources
Construction rateModel estimate — construction loan rate; replace with cited source unverified · low
Permanent rateModel estimate — 30-yr jumbo rate; replace with cited source unverified · low
LTVModel estimate — construction-to-perm LTV; replace with cited source unverified · lowA ratio, not a cost: lower LTV means more family equity. Columns are the low-/mid-/high-cost scenarios; the low-cost scenario pairs cheaper construction with a tighter 70% lender.
Closing costsModel estimate — lot closing costs; replace with cited source unverified · low
Construction monthsModel estimate — build duration in Mt. CB (short season); replace with cited source unverified · low

Construction months: 12 / 14 / 18 unverified · low

Carry assumptions and sources
Property tax rateModel estimate — Gunnison County effective residential tax rate; replace with cited source unverified · low
HOA duesModel estimate — Prospect HOA dues; replace with cited source unverified · lowAsk agent for current dues.
InsuranceModel estimate — homeowners insurance, mountain custom; replace with cited source unverified · low
UtilitiesModel estimate — gas/electric/water/internet; replace with cited source unverified · low
Snow removalModel estimate — driveway & roof snow removal; replace with cited source unverified · low
Maintenance reserveModel estimate — maintenance reserve; replace with cited source unverified · low
Rental income from the lock-off is not yet modeled (Phase 2). Monthly figures above are gross carrying costs.